I have a spreadsheet that our different locations used for scheduling. For
each day of the week, the manager selects a start time and an end time. The
total hours then calculates in the last column using a SUM formula. What has
been requested is that an error pop up when that SUM forumula calculates
hours that are greater than 40. I've tried every variation in data
validation that I can think of but I can't get anything to work. Any
suggestions welcome. I am working in Excel 2002. Thanks!
  #2   Report Post  
Posted to microsoft.public.excel.misc
Rich Stanek
 
Posts: n/a
Default Data Validation using whole numbers from formulas

You could try using an If statement in the column next to the sum column that
will show if the amount is over 40 hours: Example.......if(B240,"problem,"
") This formula will show the word problem when it is over 40, and nothing
if it is under 40.

"brodiemac" wrote:

I have a spreadsheet that our different locations used for scheduling. For
each day of the week, the manager selects a start time and an end time. The
total hours then calculates in the last column using a SUM formula. What has
been requested is that an error pop up when that SUM forumula calculates
hours that are greater than 40. I've tried every variation in data
validation that I can think of but I can't get anything to work. Any
suggestions welcome. I am working in Excel 2002. Thanks!

  #3   Report Post  
Posted to microsoft.public.excel.misc
Peo Sjoblom
 
Posts: n/a
Default Data Validation using whole numbers from formulas

=SUM($A$1:$A$5)<=--"40:00"

I assume you apply it in the cell where the end time is entered

of course if you are not using time values use <=40 instead


--

Regards,

Peo Sjoblom

http://nwexcelsolutions.com


"brodiemac" wrote in message
...
I have a spreadsheet that our different locations used for scheduling. For
each day of the week, the manager selects a start time and an end time.
The
total hours then calculates in the last column using a SUM formula. What
has
been requested is that an error pop up when that SUM forumula calculates
hours that are greater than 40. I've tried every variation in data
validation that I can think of but I can't get anything to work. Any
suggestions welcome. I am working in Excel 2002. Thanks!



  #4   Report Post  
Posted to microsoft.public.excel.misc
brodiemac
 
Posts: n/a
Default Data Validation using whole numbers from formulas

Your suggestion didn't work until I tried to remove the <=--"40:00", then the
validation messages would pop up. Strange. Also, just as an FYI, the totals
display in whole numbers, not in a time format.

"Peo Sjoblom" wrote:

=SUM($A$1:$A$5)<=--"40:00"

I assume you apply it in the cell where the end time is entered

of course if you are not using time values use <=40 instead


--

Regards,

Peo Sjoblom

http://nwexcelsolutions.com


"brodiemac" wrote in message
...
I have a spreadsheet that our different locations used for scheduling. For
each day of the week, the manager selects a start time and an end time.
The
total hours then calculates in the last column using a SUM formula. What
has
been requested is that an error pop up when that SUM forumula calculates
hours that are greater than 40. I've tried every variation in data
validation that I can think of but I can't get anything to work. Any
suggestions welcome. I am working in Excel 2002. Thanks!




  #5   Report Post  
Posted to microsoft.public.excel.misc
brodiemac
 
Posts: n/a
Default Data Validation using whole numbers from formulas

I need to clarify a bit. For each day, when a start and end time is entered,
a third column in that day calculates the total hours for that day. The
final total sums all the daily hours column to get the total hours. The
final total is when I want to use the validation so that a pop up window
shows when the total sum of hours is greater than 40.

"brodiemac" wrote:

I have a spreadsheet that our different locations used for scheduling. For
each day of the week, the manager selects a start time and an end time. The
total hours then calculates in the last column using a SUM formula. What has
been requested is that an error pop up when that SUM forumula calculates
hours that are greater than 40. I've tried every variation in data
validation that I can think of but I can't get anything to work. Any
suggestions welcome. I am working in Excel 2002. Thanks!

Reply
Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules

Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
ranking query JaimeTimbrell Excel Discussion (Misc queries) 2 February 16th 06 08:09 AM
Formulas not recognizing new data malakingaso Excel Discussion (Misc queries) 1 February 8th 06 07:27 PM
Inserting a new line when external data changes Rental Man Excel Discussion (Misc queries) 0 January 11th 06 07:05 PM
Sort pages? David Excel Discussion (Misc queries) 15 May 13th 05 11:33 PM
formulas for transferring data validation information in excel 200 Tony Excel Worksheet Functions 1 November 9th 04 10:21 PM


All times are GMT +1. The time now is 10:28 PM.

Powered by vBulletin® Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
Copyright ©2004-2024 ExcelBanter.
The comments are property of their posters.
 

About Us

"It's about Microsoft Excel"