Somebody please help me as this is driving me insane!
What i would like excel to do is automatically input the date that is 6
weeks after the date i input!
For example, in column 1 i put the date 01/01/2006, in column 2 i would like
the date 6 weeks after that to automatically appear, which would be 12/02/2006

Is this type of thing possible to do on excel? And if it it will the
computer undertsand weeks or will it have to be in days (so 6 weeks would be
42 days).

I hope someone can shed some light on this for me. If you need any further
clairification then please ask.

Thank you

Don Guillett

Working out the date
 
look here
http://www.cpearson.com/excel/weeknum.htm

--
Don Guillett
SalesAid Software

"Spiller" wrote in message
...
Somebody please help me as this is driving me insane!
What i would like excel to do is automatically input the date that is 6
weeks after the date i input!
For example, in column 1 i put the date 01/01/2006, in column 2 i would
like
the date 6 weeks after that to automatically appear, which would be
12/02/2006

Is this type of thing possible to do on excel? And if it it will the
computer undertsand weeks or will it have to be in days (so 6 weeks would
be
42 days).

I hope someone can shed some light on this for me. If you need any further
clairification then please ask.

Thank you




Pete_UK

Working out the date
 
If you put your date in A1, enter this formula in B1:

=IF(A1="","",A1+42)

Format this cell as a date in the way you wish and copy down the column
- if you haven't entered a date in column A then the column B will be
blank.

Hope this helps.

Pete


OZDOC1050

Working out the date
 
you could try
1/01/2006 12/02/2006

both cells formatted to date, date typed into first cell , formula in second
cell =
=A1+42
and your done.

--
(][ THIS EMAIL HAS BEEN SCANNED BY NORTON ANTIVIRUS ][)
"Spiller" wrote in message
...
Somebody please help me as this is driving me insane!
What i would like excel to do is automatically input the date that is 6
weeks after the date i input!
For example, in column 1 i put the date 01/01/2006, in column 2 i would
like
the date 6 weeks after that to automatically appear, which would be
12/02/2006

Is this type of thing possible to do on excel? And if it it will the
computer undertsand weeks or will it have to be in days (so 6 weeks would
be
42 days).

I hope someone can shed some light on this for me. If you need any further
clairification then please ask.

Thank you




Spiller

Working out the date
 
Thank you so much Pete! My headache has now disappeared!!!

"Pete_UK" wrote:

If you put your date in A1, enter this formula in B1:

=IF(A1="","",A1+42)

Format this cell as a date in the way you wish and copy down the column
- if you haven't entered a date in column A then the column B will be
blank.

Hope this helps.

Pete



Pete_UK

Working out the date
 
Thanks for the feedback. Glad to hear you are feeling better!

Pete



All times are GMT +1. The time now is 12:06 AM.

Powered by vBulletin® Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
ExcelBanter.com