I need a formula that will calculate future dates for me. If I were to insert
todays date,(as an example) 13-june-2005 into excel, I need it to calculate 6
weeks, 6 months, 1 year, 2 years, 3 years and 4 years ahead of the date
specified. On top of this, the future dates cannot land on a weekend or a
holiday. I am aware of the WORKDAY function but don't know how to use it. My
excel experience with formula's is limited. Very basic steps is required.

  #2   Report Post  
Ron Rosenfeld
 
Posts: n/a
Default

On Mon, 13 Jun 2005 10:32:04 -0700, mike richard <mike
wrote:

I need a formula that will calculate future dates for me. If I were to insert
todays date,(as an example) 13-june-2005 into excel, I need it to calculate 6
weeks, 6 months, 1 year, 2 years, 3 years and 4 years ahead of the date
specified. On top of this, the future dates cannot land on a weekend or a
holiday. I am aware of the WORKDAY function but don't know how to use it. My
excel experience with formula's is limited. Very basic steps is required.


So long as you are going to use the ATP, then the EDATE function is the
simplest way of adding months to your initial date. It takes care of the
problem that can occur when adding six months and not having the resultant
month have enough days. Or adding years to 29 Feb 2004.

To use the WORKDAY function so as to avoid falling on a weekend or holiday, you
need to have a range, which you may name Holidays, that contains a list of all
the Holiday dates. You then subtract 1 from the calculated date, and add 1
workday to that result. The result will be the first non-holiday, non-weekend
after your computed date. (If you want the day before, then add 1 to the
calculated date and subtract 1 workday).


A2: Initial Date
B2: =workday(A2+42-1,1,Holidays) (6 weeks)
C2: =workday(edate(A2,6)-1,1,Holidays) (6 months)
D2: =workday(edate(A2,12)-1,1,Holidays) (1 year or 12 months)
E2: =workday(edate(A2,24)-1,1,Holidays) (2 years or 24 months)
F2: =workday(edate(A2,36)-1,1,Holidays) (3 years or 36 months)
G2: =workday(edate(A2,48)-1,1,Holidays) (4 years or 48 months)

This should get you started. Let me know how it works out.


--ron
  #3   Report Post  
mike richard
 
Posts: n/a
Default

Thanks Ron, that worked perfectly.
Enjoy yourself.
Mike

"Ron Rosenfeld" wrote:

On Mon, 13 Jun 2005 10:32:04 -0700, mike richard <mike
wrote:

I need a formula that will calculate future dates for me. If I were to insert
todays date,(as an example) 13-june-2005 into excel, I need it to calculate 6
weeks, 6 months, 1 year, 2 years, 3 years and 4 years ahead of the date
specified. On top of this, the future dates cannot land on a weekend or a
holiday. I am aware of the WORKDAY function but don't know how to use it. My
excel experience with formula's is limited. Very basic steps is required.


So long as you are going to use the ATP, then the EDATE function is the
simplest way of adding months to your initial date. It takes care of the
problem that can occur when adding six months and not having the resultant
month have enough days. Or adding years to 29 Feb 2004.

To use the WORKDAY function so as to avoid falling on a weekend or holiday, you
need to have a range, which you may name Holidays, that contains a list of all
the Holiday dates. You then subtract 1 from the calculated date, and add 1
workday to that result. The result will be the first non-holiday, non-weekend
after your computed date. (If you want the day before, then add 1 to the
calculated date and subtract 1 workday).


A2: Initial Date
B2: =workday(A2+42-1,1,Holidays) (6 weeks)
C2: =workday(edate(A2,6)-1,1,Holidays) (6 months)
D2: =workday(edate(A2,12)-1,1,Holidays) (1 year or 12 months)
E2: =workday(edate(A2,24)-1,1,Holidays) (2 years or 24 months)
F2: =workday(edate(A2,36)-1,1,Holidays) (3 years or 36 months)
G2: =workday(edate(A2,48)-1,1,Holidays) (4 years or 48 months)

This should get you started. Let me know how it works out.


--ron

  #4   Report Post  
Ron Rosenfeld
 
Posts: n/a
Default

On Mon, 13 Jun 2005 13:26:07 -0700, mike richard
wrote:

Thanks Ron, that worked perfectly.
Enjoy yourself.
Mike



You're welcome. Thanks for the feedback.

--ron
Reply
Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules

Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
calculating excel spreadsheet files for pensions and life insurance (including age calculation sheets) RICHARD Excel Worksheet Functions 1 March 15th 05 05:49 PM
Quick date calculation functions Grey Excel Worksheet Functions 3 March 14th 05 03:01 AM
Date Math Problem Dkline Excel Worksheet Functions 4 March 4th 05 04:11 PM
date calculation Juco Excel Worksheet Functions 1 February 12th 05 05:31 PM
Date Calculation Mukund Excel Worksheet Functions 3 January 11th 05 11:29 AM


All times are GMT +1. The time now is 04:58 PM.

Powered by vBulletin® Copyright ©2000 - 2025, Jelsoft Enterprises Ltd.
Copyright ©2004-2025 ExcelBanter.
The comments are property of their posters.
 

About Us

"It's about Microsoft Excel"