Hi, I'd like to compute the duration of a series of tasks by subtracting the
end date from the start date--but also removing the weekend days to give an accurate 'days' count. Thanks in advance for your replies, JP |
#2
![]()
Posted to microsoft.public.excel.misc
|
|||
|
|||
![]()
You simply need to use the worksheet function, "networkdays", you can get
more details from the help file on this function. "JP" wrote: Hi, I'd like to compute the duration of a series of tasks by subtracting the end date from the start date--but also removing the weekend days to give an accurate 'days' count. Thanks in advance for your replies, JP |
#3
![]()
Posted to microsoft.public.excel.misc
|
|||
|
|||
![]()
Thanks, JH - but it looks like my version of Excel doesn't include this handy
function, unless I missed something. I use 2003 SP3 - is there an alternate way of doing this? Thanks again, JP "JH" wrote: You simply need to use the worksheet function, "networkdays", you can get more details from the help file on this function. "JP" wrote: Hi, I'd like to compute the duration of a series of tasks by subtracting the end date from the start date--but also removing the weekend days to give an accurate 'days' count. Thanks in advance for your replies, JP |
#4
![]()
Posted to microsoft.public.excel.misc
|
|||
|
|||
![]()
Did you look up "networkdays" in Excel help, as JH suggested? What did it
tell you? Why do you think that you don't have the function? -- David Biddulph "JP" wrote in message ... Thanks, JH - but it looks like my version of Excel doesn't include this handy function, unless I missed something. I use 2003 SP3 - is there an alternate way of doing this? Thanks again, JP "JH" wrote: You simply need to use the worksheet function, "networkdays", you can get more details from the help file on this function. "JP" wrote: Hi, I'd like to compute the duration of a series of tasks by subtracting the end date from the start date--but also removing the weekend days to give an accurate 'days' count. Thanks in advance for your replies, JP |
#5
![]()
Posted to microsoft.public.excel.misc
|
|||
|
|||
![]()
It sounds like you want to use =networkdays()
If you're using xl2003 or below, you'll have to have the analysis toolpak loaded. Excel's help for =networkdays() will show you how. JP wrote: Hi, I'd like to compute the duration of a series of tasks by subtracting the end date from the start date--but also removing the weekend days to give an accurate 'days' count. Thanks in advance for your replies, JP -- Dave Peterson |
Reply |
Thread Tools | Search this Thread |
Display Modes | |
|
|
![]() |
||||
Thread | Forum | |||
Making weekend days working days - the system cuts the working tim | Excel Discussion (Misc queries) | |||
duration days | Excel Discussion (Misc queries) | |||
Formula to Remove Weekend Days | Excel Discussion (Misc queries) | |||
Excel running date formula minus weekend days | Excel Worksheet Functions | |||
Weekend days other than Sat Sun | Excel Worksheet Functions |