Home |
Search |
Today's Posts |
|
#1
![]()
Posted to microsoft.public.excel.misc
|
|||
|
|||
![]()
I am currently trying to use Solver to help optimize some water pump usage.
I have three locations where these pumps are located. If the water demand can be met by two sites alone i would prefer to only use those two sites not the three. For instance Site A - 100gpm Site B - 100 gpm Site C - 100gpm I need 175 gpm so solver would tell me 100% use on Site A, 75% use on Site B and 0% on site C. Currently Solver is giving me Site A =58.33%, B=58.33%, and C=58.33% So is there i way i can do this? |
#2
![]()
Posted to microsoft.public.excel.misc
|
|||
|
|||
![]()
Great question !
Point 1) when the required amount is <=200, use Solver with only sites A and B Point 2) if you start with initial values (guesses) which are equal Solver gives a solution with equal values. I solved your problem by starting Site A at 100000% (any very big number), B at zero; and varied only these two; I got 100% and 75% A more sophisticated solution would use VBA to set initial values and to decide how many sites to use for a solution. Do not try to make a Solver model with IFs or other non-smooth functions -- Bernard V Liengme Microsoft Excel MVP http://people.stfx.ca/bliengme remove caps from email "Soccer boy" wrote in message ... I am currently trying to use Solver to help optimize some water pump usage. I have three locations where these pumps are located. If the water demand can be met by two sites alone i would prefer to only use those two sites not the three. For instance Site A - 100gpm Site B - 100 gpm Site C - 100gpm I need 175 gpm so solver would tell me 100% use on Site A, 75% use on Site B and 0% on site C. Currently Solver is giving me Site A =58.33%, B=58.33%, and C=58.33% So is there i way i can do this? |
#3
![]()
Posted to microsoft.public.excel.misc
|
|||
|
|||
![]()
Here is a non-solver solution
Here is my worksheet Site A 100 100% need 250 Site B 100 100% sumproduct 250 Site C 100 50% B1:B3 hold the pump max capacity C1:C3 hold the percentages E1 holds the required amount E2 has the formula =SUMPRODUCT(B1:B3,C1:C3) This subroutine varied the appropriate pump percentage to make E1=E2 I used steps of 0.01% but you could make it finer Sub pump() mygoal = Range("E1") Range("C1:C3") = 0 If mygoal 300 Then MsgBox "Not possible" Exit Sub End If If mygoal <= 100 Then mypump = 1 ElseIf mygoal <= 200 Then Range("C1") = 1 mypump = 2 Else Range("C1:C2") = 1 mypump = 3 End If Do While Range("E2") < Range("E1") Cells(mypump, "C") = Cells(mypump, "C") + 0.01 Loop End Sub -- Bernard V Liengme Microsoft Excel MVP http://people.stfx.ca/bliengme remove caps from email "Soccer boy" wrote in message ... I am currently trying to use Solver to help optimize some water pump usage. I have three locations where these pumps are located. If the water demand can be met by two sites alone i would prefer to only use those two sites not the three. For instance Site A - 100gpm Site B - 100 gpm Site C - 100gpm I need 175 gpm so solver would tell me 100% use on Site A, 75% use on Site B and 0% on site C. Currently Solver is giving me Site A =58.33%, B=58.33%, and C=58.33% So is there i way i can do this? |
#4
![]()
Posted to microsoft.public.excel.misc
|
|||
|
|||
![]()
Hi. For this small problem, note that you do not have any constraints.
Therefore, there are an infinite number of solutions. One quick solution with 3 equal values (100 gpm) is to assign a penalty weight for each station. For example, assign a penalty of 1 to #1, 2 to #2, ..etc Change the logic to "Minimize the penalty" with the constraint that Sumproduct(GPM, Percentage) = 175. Now, you will fill station 1 first, then start using station 2, etc. Make sure the option for "assume non-negative" is selected. ) The "General" technique for selecting "2 out of 3" (or whatever) is to assign 3 cells to hold "Binary" cells (0 or 1 in Solver) Target: Sumproduct(GPM, Percentage, Binary) = 175 Subject to: Binary cells = Bin (Binary) Sum(Binary) = 2 (I like to use <= 2.1 to account for any rounding issues) For each, one needs to add the constraint that Percentages <= 1 Good luck. = = = HTH Dana DeLouis Soccer boy wrote: I am currently trying to use Solver to help optimize some water pump usage. I have three locations where these pumps are located. If the water demand can be met by two sites alone i would prefer to only use those two sites not the three. For instance Site A - 100gpm Site B - 100 gpm Site C - 100gpm I need 175 gpm so solver would tell me 100% use on Site A, 75% use on Site B and 0% on site C. Currently Solver is giving me Site A =58.33%, B=58.33%, and C=58.33% So is there i way i can do this? |
Reply |
Thread Tools | Search this Thread |
Display Modes | |
|
|
![]() |
||||
Thread | Forum | |||
Solver | Excel Discussion (Misc queries) | |||
how to add-in solver without cd | Excel Discussion (Misc queries) | |||
Solver | Excel Discussion (Misc queries) | |||
Interesting Solver problem (Solver encounters an error) | Excel Discussion (Misc queries) | |||
Solver help | Excel Worksheet Functions |