Good day all.
I am trying to create a milestone chart for a Procurement Strategy, this will be a set of say 12 activities, but i want to represent the activities on the X axis and show the Dates on the Y axis with a diamond shape to indicate the actual dates. Is there a method that i can use to generate this? So if i have an activity happening on 22nd Dec 2008 i will have a diamond shape showing on that date line? Thanks all |
Thread Tools | Search this Thread |
Display Modes | |
|
|
![]() |
||||
Thread | Forum | |||
Hi, I wnt to plt graph for Nonnumerical data (Milestone)Possible? | Charts and Charting in Excel | |||
How to add up costs per resource per milestone for a report | Excel Worksheet Functions | |||
how to create a milestone chart | Charts and Charting in Excel | |||
summary of milestone | Excel Worksheet Functions | |||
sample of a milestone tracker in excel | Excel Discussion (Misc queries) |