Percentage of deviance..two cells!
Hi - total brain freeze.
If I have two cells, say cells C1 and C20 - and in C1 is a projected output figure, for example 19,000 and in C20 is the eventual action output which was 19,568 - how would I go about popping in a formula to C21 to show the difference in percent between the forecast amount and the actual figure?! |
Percentage of deviance..two cells!
Try this:
=(C20-C1)/C1 Format the cell as percentage. Hope this helps. Pete On Oct 3, 1:21*pm, GD wrote: Hi - total brain freeze. If I have two cells, say cells C1 and C20 - and in C1 is a projected output figure, for example 19,000 and in C20 is the eventual action output which was 19,568 - how would I go about popping in a formula to C21 to show the difference in percent between the forecast amount and the actual figure?! |
Percentage of deviance..two cells!
Hi,
Formatted as % this would show your actual to be 3.46% over budget =(C20-C1)/C1 Mike "GD" wrote: Hi - total brain freeze. If I have two cells, say cells C1 and C20 - and in C1 is a projected output figure, for example 19,000 and in C20 is the eventual action output which was 19,568 - how would I go about popping in a formula to C21 to show the difference in percent between the forecast amount and the actual figure?! |
Percentage of deviance..two cells!
Many thanks to you both
"GD" wrote: Hi - total brain freeze. If I have two cells, say cells C1 and C20 - and in C1 is a projected output figure, for example 19,000 and in C20 is the eventual action output which was 19,568 - how would I go about popping in a formula to C21 to show the difference in percent between the forecast amount and the actual figure?! |
All times are GMT +1. The time now is 04:23 AM. |
Powered by vBulletin® Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
ExcelBanter.com