Dear Excel Expert User,

I have in sheet 1 a list of holidays : 01/01/2007 in A1, 25/12/2007 in A2
etc...
In Sheet 2, I have in A1 a start date and time and in B1 an end date and time.
I would like to calculate the lead time between B1 and A1, excluding the
holidays dates in sheet 1.

Thanks a lot,

Excel Dubai
  #2   Report Post  
Posted to microsoft.public.excel.misc
external usenet poster
 
Posts: 4,339
Default How to exlude holidays from a range of dates

Go to Tools=Addins=Check "Analysis Toolpak" ATP)

Then look at NETWORKDAYS function (ATP required)

This excludes weekends as well as holidays.

HTH

"Excel Dubai" wrote:

Dear Excel Expert User,

I have in sheet 1 a list of holidays : 01/01/2007 in A1, 25/12/2007 in A2
etc...
In Sheet 2, I have in A1 a start date and time and in B1 an end date and time.
I would like to calculate the lead time between B1 and A1, excluding the
holidays dates in sheet 1.

Thanks a lot,

Excel Dubai

  #3   Report Post  
Posted to microsoft.public.excel.misc
external usenet poster
 
Posts: 10
Default How to exlude holidays from a range of dates

Dear Toppers,

The reason why netwook days will not work is because it takes into
consideration the western week ends which are Starurday and Sunday. In middle
east, the week ends are Friday and Saturday.
Also, Network days takes into consideration full days whereas I want to
calculate a leadtime in Days, Hours and Minutes.

Thanks again

Excel Dubai

"Toppers" wrote:

Go to Tools=Addins=Check "Analysis Toolpak" ATP)

Then look at NETWORKDAYS function (ATP required)

This excludes weekends as well as holidays.

HTH

"Excel Dubai" wrote:

Dear Excel Expert User,

I have in sheet 1 a list of holidays : 01/01/2007 in A1, 25/12/2007 in A2
etc...
In Sheet 2, I have in A1 a start date and time and in B1 an end date and time.
I would like to calculate the lead time between B1 and A1, excluding the
holidays dates in sheet 1.

Thanks a lot,

Excel Dubai

Reply
Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules

Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
Getting and error while calculate business hours between 2 dates with holidays. [email protected] Excel Worksheet Functions 4 April 17th 07 08:08 PM
Take an average of a range of cells but exlude blanks from that av B G Excel Discussion (Misc queries) 4 October 12th 06 02:46 PM
Dates with Holidays question HJ Excel Discussion (Misc queries) 1 March 31st 06 03:08 AM
fill a series of dates excluding holidays gsh20 Excel Worksheet Functions 1 August 25th 05 12:33 AM
Skip holidays falling between two dates amit Excel Worksheet Functions 2 April 18th 05 02:09 PM


All times are GMT +1. The time now is 04:29 PM.

Powered by vBulletin® Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
Copyright ©2004-2024 ExcelBanter.
The comments are property of their posters.
 

About Us

"It's about Microsoft Excel"