In certain part of SE Asia, the workdays are 5.5. .5 days means Sat morning
with alternate Sat as off day. I need a formula to calculate leave for
staffs. I have used NETWORKDAYS to calcate the start date and end date and
public holidays but the result exclude the alternate workday of .5. Please
help. Thanks

Reply
Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules

Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
Working days Andrew Mackenzie Excel Discussion (Misc queries) 8 January 3rd 07 02:39 PM
Changing working days Greg Excel Worksheet Functions 6 August 1st 06 12:25 PM
Working Days Mike Hebblewhite Excel Discussion (Misc queries) 1 January 30th 06 11:49 AM
Working Days Mike Hebblewhite Excel Discussion (Misc queries) 0 January 30th 06 11:00 AM
How to Add 5 working days Trying2Learn Excel Discussion (Misc queries) 1 June 20th 05 12:52 PM


All times are GMT +1. The time now is 08:34 PM.

Powered by vBulletin® Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
Copyright ©2004-2024 ExcelBanter.
The comments are property of their posters.
 

About Us

"It's about Microsoft Excel"