Posted to microsoft.public.excel.misc
|
|||
|
|||
![]()
On Wed, 3 Jan 2007 12:42:03 +0000, "JMay" wrote:
With A1:A4 holding: 11/27/2006 11/28/2006 11/29/2006 11/30/2006 When I enter in B1 and Copy down =WORKDAY(A1+29,1,Holidays) I get in B1:B4: 12/27/2006 12/28/2006 12/29/2006 01/01/2007 <<< Not sure why this one?? Any ideas what's going wrong? My Holiday range only includes 10/31/2006 and 12/25/2006 (2 cells) Thanks, If you don't have 1 Jan listed in your Holiday range, and it is not a weekend day (Saturday Sunday), Excel cannot know that you want to consider it a holiday. 1 Jan 2007 was a Monday. --ron |
Thread Tools | Search this Thread |
Display Modes | |
|
|
![]() |
||||
Thread | Forum | |||
Adding Working Days to a Formula | Excel Discussion (Misc queries) | |||
How do you add 40 working days to a date | Excel Discussion (Misc queries) | |||
Working days left in the month compared to previous months | Excel Worksheet Functions | |||
calculate number of working days | Excel Worksheet Functions | |||
Working time and days | Excel Worksheet Functions |