Is there a way to split a task unequally between resources. As an example;
task 1 requires 20 hrs work. I want to assign worker 1 4 hours of task 1 and
worker 2, 16 hrs of the task. can this be done using only one task?
Reply
Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules

Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
task sharing DAS Excel Discussion (Misc queries) 0 November 29th 06 05:04 PM
task sharing tim m Excel Discussion (Misc queries) 0 November 29th 06 04:59 PM
Best Approach to Worksheet Synchronization mjones Excel Discussion (Misc queries) 7 November 8th 06 11:39 AM
Sharing Worksheet cannot complete task Spirit130 Excel Worksheet Functions 0 October 6th 05 01:55 PM
loop trough e-mail address list to send task lists with outlook Paul. Excel Discussion (Misc queries) 2 April 14th 05 11:48 AM


All times are GMT +1. The time now is 06:19 PM.

Powered by vBulletin® Copyright ©2000 - 2025, Jelsoft Enterprises Ltd.
Copyright ©2004-2025 ExcelBanter.
The comments are property of their posters.
 

About Us

"It's about Microsoft Excel"