Hi,

Sounds complicated, but will save a heap of time for me...

I've got some data (actually exported from MS Project) in the following
format:

task name | duration | start date | finish date |
level
---------------------------------------------------------------------------------------------------
task 1 | x | 1/1/6 |
30/1/6 | 1
task 2 | y | 5/1/6 |
20/1/6 | 2
milestone 1 | z | 25/1/6 | 15/1/6
| 3


and I want to roll these up into a gantt style chart (for one reason or
another, this has to be done in excel rather than project...)... I
would like the chart to look something like this:


|
|##################### = task 1
| #######()###### = task 2 with it's embedded
milestone
|
|
|
|
|
|
|
|
--------------------------------------------------



ie, task one (at level one) has a number of lower level tasks (at level
2) beneath it... each of these have one or more milestones (at level
three) in them...

I'm nowhere near expert at excel charting and this is proving to be a
real challenge - I've got over 200 level one tasks so *really* don't
want to have to do it all by hand!


Many thanks,

Chris

  #2   Report Post  
Posted to microsoft.public.excel.charting
Jon Peltier
 
Posts: n/a
Default horrifyingly difficult excel chart / gantt question...

Here is an article showing rudimentary Gantt charting in Excel:

http://pubs.logicalexpressions.com/P...cle.asp?ID=343

and this adds a few advanced features:

http://peltiertech.com/Excel/Charts/GanttChart.html

- Jon
-------
Jon Peltier, Microsoft Excel MVP
Peltier Technical Services
Tutorials and Custom Solutions
http://PeltierTech.com/
_______


wrote in message
oups.com...
Hi,

Sounds complicated, but will save a heap of time for me...

I've got some data (actually exported from MS Project) in the following
format:

task name | duration | start date | finish date |
level
---------------------------------------------------------------------------------------------------
task 1 | x | 1/1/6 |
30/1/6 | 1
task 2 | y | 5/1/6 |
20/1/6 | 2
milestone 1 | z | 25/1/6 | 15/1/6
| 3


and I want to roll these up into a gantt style chart (for one reason or
another, this has to be done in excel rather than project...)... I
would like the chart to look something like this:


|
|##################### = task 1
| #######()###### = task 2 with it's embedded
milestone
|
|
|
|
|
|
|
|
--------------------------------------------------



ie, task one (at level one) has a number of lower level tasks (at level
2) beneath it... each of these have one or more milestones (at level
three) in them...

I'm nowhere near expert at excel charting and this is proving to be a
real challenge - I've got over 200 level one tasks so *really* don't
want to have to do it all by hand!


Many thanks,

Chris



Reply
Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules

Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
shrink excel chart area mcarrington Excel Discussion (Misc queries) 0 January 5th 06 08:57 PM
Chart Property Confusion Arturo Charts and Charting in Excel 4 December 16th 05 05:13 AM
Updating Excel OLE chart data in PPT from Excel Hari Prasadh Charts and Charting in Excel 5 July 26th 05 08:52 PM
Excel 2002 chart does not update when worksheet data changes proquant Charts and Charting in Excel 1 June 15th 05 12:23 AM
Difficult Excel Question [email protected] Excel Discussion (Misc queries) 2 January 27th 05 12:10 PM


All times are GMT +1. The time now is 04:01 AM.

Powered by vBulletin® Copyright ©2000 - 2025, Jelsoft Enterprises Ltd.
Copyright ©2004-2025 ExcelBanter.
The comments are property of their posters.
 

About Us

"It's about Microsoft Excel"