How do I create vertical lines in a line chart?
Hi everybody-
I have created a line chart with 20 weeks of data plotted across the X-axis (each data point corresponds to the response rates to a direct mail campaign). I now want to plot two vertical lines showing the start of the campaign (week 4) and the end of the campaign (week 16). I know I can manually draw a line, but these charts need to be updated on a regualr basis, and it will take me hours to manually move the lines on the 100 or so charts I produce. So I want to have someway to specify a start date and end date, and have the charts update automatically. Thanks, JM |
#2
|
|||
|
|||
one way to do it if this is an XY plot with the X data being dates
add the same data set to each graph std 0 'std is the start date spd 0 'spd is the stop date on the charts select this data set and select y error bars select the bar you want and set its max value to the max you want the chart to show. when ever you want to update just change the std and spd cells "jrmruz" wrote: Hi everybody- I have created a line chart with 20 weeks of data plotted across the X-axis (each data point corresponds to the response rates to a direct mail campaign). I now want to plot two vertical lines showing the start of the campaign (week 4) and the end of the campaign (week 16). I know I can manually draw a line, but these charts need to be updated on a regualr basis, and it will take me hours to manually move the lines on the 100 or so charts I produce. So I want to have someway to specify a start date and end date, and have the charts update automatically. Thanks, JM |
#3
|
|||
|
|||
Thank you! It worked!
"bj" wrote: one way to do it if this is an XY plot with the X data being dates add the same data set to each graph std 0 'std is the start date spd 0 'spd is the stop date on the charts select this data set and select y error bars select the bar you want and set its max value to the max you want the chart to show. when ever you want to update just change the std and spd cells "jrmruz" wrote: Hi everybody- I have created a line chart with 20 weeks of data plotted across the X-axis (each data point corresponds to the response rates to a direct mail campaign). I now want to plot two vertical lines showing the start of the campaign (week 4) and the end of the campaign (week 16). I know I can manually draw a line, but these charts need to be updated on a regualr basis, and it will take me hours to manually move the lines on the 100 or so charts I produce. So I want to have someway to specify a start date and end date, and have the charts update automatically. Thanks, JM |
Reply |
Thread Tools | Search this Thread |
Display Modes | |
|
|
Similar Threads | ||||
Thread | Forum | |||
How to create combination stacked area and line chart? | Charts and Charting in Excel | |||
Formatting lines between data points in a line chart | Charts and Charting in Excel | |||
Lines not visible in an Excel line chart | Charts and Charting in Excel | |||
create space in line chart between points, linked to pivot table | Charts and Charting in Excel | |||
pivot table multi line chart | Charts and Charting in Excel |