CALCULATE BETWEEN TWO DATES EXCLUDING WEEKENDS
What results are you expecting?
11/20/09...11/23/09 = 2 which is correct
11/2/09...11/5/09 = 4 which is correct
If you want a result of 3 for 11/2/09...11/5/09 then which date don't you
want to count? The start date or the end date?
What results do you expect for these dates:
11/2/2009 (Mon) - 11/2/2009 (Mon)
11/1/2009 (Sun) - 11/2/2009 (Mon)
11/6/2009 (Fri) - 11/7/2009 (Sat)
--
Biff
Microsoft Excel MVP
"CYNTHIA" wrote in message
...
A) B)
11/20/09 11/23/09
11/2/09 11/5/09
When I use the Network formula it says 4 days which is incorrect for the
11.20.09 date.
I use the formula NETWORKDAYS(A1,B1)
also when i use to calculate 11/2/09 and 11/5/09 which i know are not
weekend dates but regular business dates it says 4 days which is wrong its
3
days
I use the formula NETWORKDAYS(A1,B1)
Please help me
|