Date percent complete as of today
Try the below.
=(TODAY()-J2)/(K2-J2)%
If this post helps click Yes
---------------
Jacob Skaria
"deb" wrote:
Column J Column K
Project Start Project End
1-Jan-06 5-May-10
I need the percent complete as of todays date.
Any Ideas?
--