Default Date percent complete as of today

=(today()-j2)/(k2-j2)
Format as percent

Regards,
Fred

"deb" wrote in message
...
Column J Column K
Project Start Project End
1-Jan-06 5-May-10

I need the percent complete as of todays date.

Any Ideas?
--