Default Excel formula to spread data over a period of time

Going with the idea that if your project covers x months, and you have y
hours, formula would be y / x:

=Hours/DATEDIF(Start_Date,End_Date,"m")

Note that this uses complete months. So, a start date of 1/15/09, and end
date of 3/1/09, would cause formula to use 1 full month, so a distribution of
40 hrs per month (since its only 1 month)
--
Best Regards,

Luke M
*Remember to click "yes" if this post helped you!*


"PMuskie" wrote:

I have a project start and end date and have calculated the amount of time
based on those dates. I have # hours that will be spent on that project. I
need to have the # hrs spread monthly over the length of the project based on
the start and end date. any help would eb appreciated.