How to calculate dates
Eduardo, thank you. That was so simple, I almost feel embarassed.
"Eduardo" wrote:
Hi Pat,
If it has to include weekends and Holidays just do
=A1+60
"Pat" wrote:
No it has to include weekends and holidays. I'm using the workday function,
which excludes weekends and holidays, and I need to figure out dates that are
60 calendar days from the date of initiaton.
A1 B1
C1
today's date 60 (calendar days) = date project to be
completed
"Niek Otten" wrote:
<includes weekends and holidays
I assume you mean exclude?
<The function will only calcuate weekdays
Which function?
Look in HELP for the WORKDAY() function
--
Kind regards,
Niek Otten
Microsoft MVP - Excel
"Pat" wrote in message
...
How would I calculate a project date 60 days from any given date that
includes weekends and holidays. The function will only calcuate weekdays.
|