Default Using Networkdays with negative numbers

VainDM,
You're Welcomed.

--
Add MS to your News Reader: news://msnews.microsoft.com
Rich/rerat
(RRR News) <message rule
<<Previous Text Snipped to Save Bandwidth When Appropriate


"VainDM" wrote in message
...
Thank You for your reply it worked perfectly cheers
-VainDM

"Rich/rerat" wrote:

If you data is set up like this
Column A Column B Column C Column D
JobID Est Fin Date Fin Date Difference

Enter the following formula in D2, and drag it down Column D:
=IF($B2=$C2,0,IF($C2<$B2,NETWORKDAYS($B2,$C2)+1,NE TWORKDAYS($B2,$C2)))

If you finish the job on time:
Column D=0
If you finish the job early:
Column D= (-)#of days
If you finish the job late:
Column D= (+)#of days

If you have a Holiday Table, in D2 use:
=IF($B2=$C2,0,IF($C2<$B2,NETWORKDAYS($B2,$C2,HolRa nge)+1,NETWORKDAYS($B2,$C2,HolRange)))

--
Add MS to your News Reader: news://msnews.microsoft.com
Rich/rerat
(RRR News) <message rule
<<Previous Text Snipped to Save Bandwidth When Appropriate


"VainDM" wrote in message
...
say i have 3 columns <ID <Est Finish Date and <Actual Finish Date and I
want an extra column that tells me how many working days before or after
the
estimated finish date the actual finish date is. I used Networkdays and
it
gave me the number of days after the estimated date minus the weekends,
however when the actual date was before the estimated date the formula
still
counted the weekends.

Does anyone know a way of stopping this from happening?