Adding 2weeks and rounding up to EOM
Hi,
Try this
=eomonth(G11+14,0)
Note that if 14 days is after the end of the current month this gives the
end date of the next month.
If you get a #NAME error then
Tools|Addins and check the analysis toolpak
Mike
"Micki" wrote:
I need to add 2 weeks to a date and round it up to the last day of the month.
G11: 6/15/2009
Add 2 weeks, but round to 6/30/2009
If I add 14 days to 6/15/2009, it returns 6/29/2009
Thank you.
|