Calculate End Date (excluding weekends and holidays)
Subtract 1... the difference is because you are thinking "counting numbers"
as opposed to "subtraction of two numbers"... 1, 2, 3, 4 5 is five counting
numbers but the difference between 1 and 5 is four.
--
Rick (MVP - Excel)
"guitaronmyback" wrote in message
...
It worked, but it seemed to add an extra day....10 workdays, starts on a
Monday and the final date was a Monday, when it should be a Friday....any
way
of fixing that?
"Rick Rothstein" wrote:
The WORKDAY function requires the Analysis ToolPak add-in to be loaded.
Click Tools/Add-Ins from Excel's menu bar and put a check mark next to
the
Analysis ToolPak item.
--
Rick (MVP - Excel)
"guitaronmyback" wrote in
message
...
Thank you for the tip, but I got the #name? as a result
"Mike H" wrote:
Hi,
Try this
=WORKDAY(B1,25,Holidays)
Where
B1=start date
25 is the days for the project
Holidays is a named range containing holoiday dates.
Mike
"guitaronmyback" wrote:
Hello,
I have a start days and a number (representing days for a given
project). I
want to calculate the end date and exclude weekends and certain
holidays.
Is this possible?
Thank you
|