Thread
:
Time multiplied by cost per hr
View Single Post
#
3
Posted to microsoft.public.excel.misc
Roger Govier[_3_]
external usenet poster
Posts: 2,480
Time multiplied by cost per hr
Hi Steve
Excel stores times a fractions of a day, so multiply your result by 24.
with time in A1, rate in B1
=A1*B1*24
--
Regards
Roger Govier
"Steve Tupper" <Steve
wrote in message
...
I want to get XL to give me the result of the following type of
calculations:
41hr 55mins (entered into a cell as 41:55:00 ?) multiplied by the rate per
hr entered in another cell as a monetary amount of say 563.50 to give the
resultant cost in a 3rd cell.
I want to be able to enter time as hrs & minutes NOT as hrs and a decimal
of
an hr.
Reply With Quote
Roger Govier[_3_]
View Public Profile
Find all posts by Roger Govier[_3_]