Work days
Thanks Mike - this is great
"Mike H" wrote:
Hi,
Networkdays would normally give an answer 1 higher than you are asking for
so perhaps this
=IF(B1<A1,networkdays(A1,B1,Holidays)+1,networkday s(A1,B1,Holidays)-1)
If your results are an error or typo use the simpler
=networkdays(A1,B1,Holidays)
Holidays is a named range containing holiday dates. If you get a NAM error
then
Tools|Addins and load the analysis toolpak.
Mike
"Bob Freeman" wrote:
Hello,
I am trying to get a formula that will calculate the number of workdays
(Monday to Friday) between two dates in the following format - if possible
this will also take into account a specified list of holidays (non-workdays),
e.g. 25/12/08, which I can specify in a list.
This will always revolve around date 1 - so if date 2 is after date 1 it
will be a positive number, if date 2 is before date one, it will be a
negative number
For example:
Date 1 Date2 No of working
days from date 1
Monday 2nd Feb Friday 30th Jan -1
Monday 2nd Feb Wednesday 4th Feb 2
Monday 2nd Feb Monday 9th Feb 5
Many thanks.
Bob
|