WORK HOURS DIFFERENCE BETWEEN TWO DATES
I have to thank you too because I was looking for this same answer!!! You're
awesome! ~Dee
"Mike H" wrote:
your welcome
"CHRISTI" wrote:
Mike - thank you this solved all; would never have figured this out by myself!
"Mike H" wrote:
Hi,
Your other response made me aware that I'd missed publich holidays so change
to this
=(NETWORKDAYS(A1,A2,C1:C8)-1)*(B2-B1)+IF(NETWORKDAYS(A2,A2),MEDIAN(MOD(A2,1),B2,B1), B2)-MEDIAN(NETWORKDAYS(A1,A1)*MOD(A1,1),B2,B1)
Where C1 to C8 is your holiday list. Just a point to note is that I have
assumed that a public holiday wouldn't be either of the dates in A1 or A2. If
these dates were public holidays then the real start/end date is a day
later/earlier and in any case I'm struggling to work it out otherwise.
Perhaps someone can enlighten us.
Mike
"CHRISTI" wrote:
I need to calculate the total WORK-hours (08:00-17:00) between two
date/time-stamps;
-excluding WEEKENDS
-excluding PUBLIC HOLIDAYS
eg#1.: A1=START DATE/TIME & A2=END DATE/TIME & A3=RESULT ([hh]:mm)
A1 11-01-2008 09:00:00
A2 11-01-2008 11:00:00
A3 02:00
eg#2.: A1=START DATE/TIME & A2=END DATE/TIME & A3=RESULT ([hh]:mm)
A1 11-01-2008 09:00:00
A2 14-01-2008 11:00:00
A3 11:00
eg#3.: A1=START DATE/TIME & A2=END DATE/TIME & A3=RESULT ([hh]:mm)
A1 14-01-2008 09:00:00
A2 16-01-2008 11:00:00
A3 20:00
|