Default Need help with formula

Hi,

The undocumented DATEDIF function has the following form:

DATEDIF(StartDate,EndDate,Unit)

Where Units are on the left in the table below and their results on the
right. Note that the Unit must be quoted - "y" for example.

y Whole years between two dates
m Whole months between two dates
d Whole days between two dates
md Number of days between two dates ignoring months
ym Number of months between two dates ignoring years
yd Number of days between two dates ignoring years

=DATEDIF(A1,A2,"Y") returns the number of whole years between the dates in
cell A1 and A2

If this helps, please click the Yes button.

Cheers,
Shane Devenshire


"WLMPilot" wrote in message
...
I have racked my brain to try and figure this out. I have a worksheet
with
the following I am having trouble with the ROUNDDOWN part of formula in
Columna J.

Col E: Monthly Pmt
Col G: Total to be paid back
Col H: Amt Pd so far
=IF(TODAY()<=R30,MIN(G30,E30*J30),MIN(G30,E30*J30) )
Col I: Balance
=IF(H30="","",G30-H30)
Col J: Pmts made
=IF(TODAY()<$Q30,0,IF(TODAY()$R30,ROUND((($R30-$Q30)/30)
+1,0),ROUNDDOWN(((TODAY()-Q30)/30),0)))
Col K: Pmts remaining
=IF(M30="N",ROUNDUP(G30/E30,0)-J30,""))
Col Q: Start Date
Col R: End Date

The formula shown shows the correct value in Column J for example 1, but
not
for example 2. I want Col J (pmts made) to equal 1 if TODAY() = Start
Date
but Col J does not equal 1 until 30 days after the start date.

EXAMPLE 1:
Pmt = $250
Total To Be Paid: $23,227.19
Start Date: 9/20/02
Pmts Made (as of 12/20/08) = 76
Pmts Remaining (as of 12/20/08) = 17

Example 2: This is a dummy example I am using to try and fix the problem
Pmt = $500
Total to be Paid: $5,000
Start Date = today's date (whatever date that is)

I want the Pmts Made (Col J) to equal 1 on the start date and to increase
by
one each month after that. I can't figure out why the formula works for
Example 1 and not Example 2. If I fix it so example 2 works, then the
PMTS
MADE in Example one goes to 77, instead of staying at 76.

NOTE: These are not calculation that involved knowing interest rates, but
simply the TOTAL amount to be paid.

Your help is GREATLY appreciated.

Les