Formula for kanban cycle usage
Hello,
I have 5 different part numbers that are on a production line and I have
listed below one of the part numbers.
part # PPC-0013, at process #3, 2 boxes (16 pcs each box) can be kept at the
line. The production is scheduled for 81 pieces an hour.
What type of formula can be used to figure up amount of kanban cards needed
and how often to pick up the kanban cards?
--
Thank you,
Angie
|