Slightly shorter:
=A1+4+((3-(WEEKDAY(A1+4,2)-5))*(WEEKDAY(A1+4,2)5))
But it will not take holidays into account like WORKDAY() does.
--
HTH
Sandy
In Perth, the ancient capital of Scotland
and the crowning place of kings
Replace @mailinator.com with @tiscali.co.uk
"muddan madhu" wrote in message
...
TRY this !!!!
suppose u have in A1 u have expected delivery date
A1 has todays date as 30/05/2008 + 4days
B1 put this formula
=IF(WEEKDAY(A1+4)=1,A1+5,IF(WEEKDAY(A1+4)=7,A1+6,A 1+4))
On May 30, 3:59 pm, des-sa wrote:
Mike,
Returns #NAME
"Mike H" wrote:
Try
=WORKDAY(TODAY(),4)
Mike
"des-sa" wrote:
please help,
suppose i want to indicate to a client that his expected delivery date
is
today + 4 days, but if that date falls on a saturday or sunday, it
should
return the first workday thereafter. is is possible, how?