Completion date
You will need a start date in order to evaluate the completion date.
Essentially:
= start_date + total_time / hrs_per_day
Hope this helps.
Pete
On Apr 25, 12:22*am, Richard
wrote:
L1 = Hours worked per day
G:G = Total time in hours
L2 = Completion date
How would you write this formula to return a completion date?
Thanks in advance!!
|