Use the NETWORKDAYS worksheet function. Make sure the
Analysis ToolPak is installed under Tools Add-Ins. See
XL help file.
HTH
Jason
Atlanta, GA
-----Original Message-----
How would you advise going about the following.
I have a column for project start dates. I have another
column indicating
duration for the project in terms of work days. How
would you calculate the
end date? Adding the duration would not account for
weekend? Thoughts?
.
|