View Single Post
  #3   Report Post  
Posted to microsoft.public.excel.worksheet.functions
PAL PAL is offline
external usenet poster
 
Posts: 200
Default More Planned and Actual Cycle Times

People input a date in one column as planned or actual. When I list the
output I need to do it by year. So, I hope to use it as a filter to show
that for all of Milestone 2 who end in 2008, the cycle time is .....Hope that
helps.

"FSt1" wrote:

hi,
what is the significance of D2 or C2 being in year x and if it isn't, then
what?

regards
FSt1

"PAL" wrote:

Here is what I have:

A2 Milestone 1 Planned
B2 Milestone 1 Actual
C2 Milestone 2 Planned
D2 Milestone 2 Actual
E2 Year (this is the year for the date in D2 or C2)

Using a nested conditionals, I would like the output to be:

Where D2 (or C2 if planned for the future) is in a Year X (from E2), then...

D2 - B2; if there is no data in D2 for calculation, then
C2 - B2; if there is no data in B2, then
C2 - A2; if no data in A2, then blank (don't want to see #value!).

Should these calculations been done separately then put into one column.....

Thanks.