How about a replacement formula that doesn't depend on the ATP?

A1 = start date
B1 = end date
C1:C5 = holiday list (if you're using the Holidays argument)

=SUMPRODUCT(--(WEEKDAY(ROW(INDIRECT(A1&":"&B1)),2)<6),
--(ISNA(MATCH(ROW(INDIRECT(A1&":"&B1)),C1:C5,0))))

If you're not using the Holidays argument:

=SUMPRODUCT(--(WEEKDAY(ROW(INDIRECT(A1&":"&B1)),2)<6))

...