Date Formulas
OK, hopefully I can explain this, so it will make sense...
Here's my example:
Let's say one of my contractors was scheduled to come on July 31, but he
can't make it until Aug. 2. This affects the rest of my schedule, and I will
have to postpone everything else on my schedule by 2 days. I've been having
to individually change each date. How can I make the dates change
automatically? The other challenge is I only schedule things on Mon. thru
Fri., so the dates need to change automatically (skipping the weekends).
I hope this makes sense!
|