=DATE(YEAR(A1),MONTH(A1)+1,20)

will return 20th of next month
of course 20 can be replaced with a cell where you put the day

--

Regards,

Peo Sjoblom

"taxmom" wrote in message
...
Hi!

I need some help.

If I type 2/1/05. Since I set the format it would show February 1, 2005
this will appear in cell A1.

However in cell A2 I will need the due date which would be the next month
March 20, 2005.

Is there a function that will look at the date in A1 and offset it to the
next month? and if so could the day (20th, 30th, etc) be adjusted?

I was trying to use the offset function but, unfortunately, I'm just
starting to work with index, match, offset, vlookup etc. Grasping the
concept of nesting is somewhat confusing still.