Date going forward
=WORKDAY(A1,60)
Format cells as date
"Donna" wrote:
I have a user who would like to calculate a date going 60 working days
forward from a date in her spreadsheet. One column contains the date of an
incident and she needs a date 60 working days ahead when the report of the
incident is due. Only working days, not total days.
She currently counts the days manually. Anyone have a solution for her?
--
Donna
|