Default Workday Formula?

What didn't work? Did you get errors or was the result incorrect?
It's part of the ATP (Analysis ToolPak) that comes with Excel/Office but it
won't install using the default installation and if it's not installed you
will get a name error. If so just go to toolsadd-ins and select it, then
plop in the installation CD when prompted


--
Regards,

Peo Sjoblom

"Fernbars" wrote in message
...
I've been trying to develop a production schedule in Excel. I'd like to
put
an end date and have Excel calculate each activities' start date based on
the
number of days needed. I can do a simple subtraction formula (end
date-#of
days) however that does not take into account weekends and holidays. I
tried
the Workday function but that didn't work.

Suggestions are most appreciated. Thank you!