Hi there.

Thanks for the formula it works fine, but I am not sure why. Can you
provide me with any explanation?
--
Thank you for your assistance.
Suzanne


"daddylonglegs" wrote:

If you want to show the workdays so far when A2 is empty then try

=NETWORKDAYS(A1,IF(A2="",TODAY(),A2))

"Suzanne" wrote:

Hi thanks for the information but that only deals with part of the problem.
Unfortunately when there is no end date the number that appears in the
running total is a minus number.

So if I have a date in cell A1 No date in cell A2 Cell A3 = NETWORKDAYS
the answer shows as -27974?

--
Thank you for your assistance.
Suzanne


"Teethless mama" wrote:

Conditional Formatting

Formula Is: =A1=15
Format as red


"Suzanne" wrote:

I currently have an Excel 2000 worksheet which tracks a project using
NETWORKDAYS to calculate the number of days taken between the start and end
date of the project.

However, I now need to have a column which shows a running total of
NETWORKDAYS taken so far (so there will be no end date) and when it reaches
15 days the number changes to red.

Can anyone help before I loose face.

Thank you for your assistance.