NETWORKDAYS
Hi, thanks for the response will try your suggestion today and get back to you.
--
Thank you for your assistance.
Suzanne
"daddylonglegs" wrote:
If you want to show the workdays so far when A2 is empty then try
=NETWORKDAYS(A1,IF(A2="",TODAY(),A2))
"Suzanne" wrote:
Hi thanks for the information but that only deals with part of the problem.
Unfortunately when there is no end date the number that appears in the
running total is a minus number.
So if I have a date in cell A1 No date in cell A2 Cell A3 = NETWORKDAYS
the answer shows as -27974?
--
Thank you for your assistance.
Suzanne
"Teethless mama" wrote:
Conditional Formatting
Formula Is: =A1=15
Format as red
"Suzanne" wrote:
I currently have an Excel 2000 worksheet which tracks a project using
NETWORKDAYS to calculate the number of days taken between the start and end
date of the project.
However, I now need to have a column which shows a running total of
NETWORKDAYS taken so far (so there will be no end date) and when it reaches
15 days the number changes to red.
Can anyone help before I loose face.