Hi there, thanks for the response.

My expectation is to have a rolling total of working days taken so
far(excluding weekends), as the maximum turnaround time for the work is 15
days. This then acts a a warning that there may be a problem.
--
Thank you for your assistance.
Suzanne


"Teethless mama" wrote:

What is your expectation of the result when there is no end date?


"Suzanne" wrote:

I currently have an Excel 2000 worksheet which tracks a project using
NETWORKDAYS to calculate the number of days taken between the start and end
date of the project.

However, I now need to have a column which shows a running total of
NETWORKDAYS taken so far (so there will be no end date) and when it reaches
15 days the number changes to red.

Can anyone help before I loose face.

Thank you for your assistance.
Suzanne