  #1   Report Post  
Jean
 
Posts: n/a
Default

It was that simple!!!! Thank you so very much!

"N Harkawat" wrote:

=workday(a1,45)
where a1 holds the start date

"Jean" wrote in message
...
What formula would I use to add 45 days to a date. I do not want to
include
any weekends in the 45-day count. In other words what is 45 days added to
February 15. This should not count Saturdays or Sundays in resulting
date.
Thanks!