"Workdays"
Is it safe to assume that the duration in Column C is working days, and you want
Column B to be the date that is the number of Column C working days after the
start date?
If so, use the Workday function:
Column B =Workday(a1,c1)
You may need to load the Analysis Toolpak to access this function
(ToolsAddins...)
--
Regards,
Fred
"GNaipaul" wrote in message
...
I have colomn with start date(Column A), Column C = duration Column B =
Column a + Column C
I would like exclude Saturday and Sunday of the week
How can I do That?
Please Help
|