Check out
http://peltiertech.com/Excel/Charts/...umnChart1.html. It
not only has a good example of this type of dynamic charting, it also has an
example for how to limit the chart to a date range as well.
The technique relies on the OFFSET function and named ranges.
WARNING: Once you start using this technique, you'll never stop!
"c991257" wrote:
Hi
In a weekly progress report I would update a quantity performed which
in turn updates an accumulated quantity.
Instead of presenting the data I present a chart showing the
performance. My problem is that everytime I add data I have to change
the source data in the chart and add the weeks cells to include those.
Is there a way around that so that I only have to enter the data and
the chart automatically takes the new data into consideration?
/Møller
--
c991257
------------------------------------------------------------------------
c991257's Profile: http://www.excelforum.com/member.php...o&userid=36549
View this thread: http://www.excelforum.com/showthread...hreadid=568507