On Tue, 18 Jul 2006 13:33:02 -0700, LOK wrote:

I did check the formating of the cells and they were dates (changed to a 5
digit number when I change to general). So, I'm unsure of what my next steps
are. the ATP is activated and this is the function I want - the NETWORKDAYS
(I tried both that and WORDAY) and yet neither works....ideas?


What does "neither works" mean? Do you get an error message? If so, what
message?

Post copies of your inputs, formula, actual output, desired output.

Do copy/paste in order to avoid typos.


--ron