=WORKDAY(A2,$C$1)
and copy down
WORKDY is part of the Analysis Toolpak, so that needs to be installed
(ToolsAddins)
--
HTH
Bob Phillips
(replace somewhere in email address with gmail if mailing direct)
"jermsalerms"
wrote in message
...
in A2:A366 i have every date of the year in mmddyyyy format
In B2:B366 i want it to return the date that is three days later.
unless it falls on a weekend. then it needs to be the following
monday.
For example:
A2 = 07/04/2006 B2 = 07/07/2006
A3 = 07/05/2006 B3 = 07/10/2006
A4 = 07/06/2006 B4 = 07/10/2006
A5 = 07/07/2006 B5 = 07/10/2006
A6 = 07/08/2006 B6 = 07/11/2006
I also want to make it is a format that cell C1 is where I put in the
amount of days later (so I can change it from 3 to 5 to 10, etc.)
Any suggestions.
--
jermsalerms
------------------------------------------------------------------------
jermsalerms's Profile:
http://www.excelforum.com/member.php...o&userid=30167
View this thread: http://www.excelforum.com/showthread...hreadid=559108