Hi!
Try this:
A1 = start date
B1 = end date
=SUMPRODUCT(--(WEEKDAY(ROW(INDIRECT(A1&":"&B1)))<6))
This doesn't account for holidays. If you need to account for holidays post
back.
Biff
"Hany ElKady" wrote in message
...
Anyone know how I can calculate the working days between two dates on a
sheet. My working week is from Sunday - Thursday, and the dates are stored
in
pairs with start date and end date.
I am leaveing VB as the last resort for this.
Any Ideas ?
--
Hany ElKady