Hi
I need to add 8 working days (excluding Saturdays and Sundays) onto a
column of existing dates all of which may be different. I know I can
use the NETWORKDAYS function to work out the difference between 2 dates
but my problem here is that I only have one date and I need to add 8
working days onto it.
Any help would be much appreciated.
Shirley Munro
--