=WORKDAY(A1,IF(B1TIME(16,0,0),5,4))
--
HTH
Bob Phillips
(remove nothere from email address if mailing direct)
"brian thompson3001 via OfficeKB.com" <u15682@uwe wrote in message
news:5cc4cd0caec36@uwe...
Hi
Trying to add 4 days to date in cell A1, without counting weekend and if
poss
bank holidays. in cell C1
example
cell a1 = date
cell b1 = time
If time after 1600 hrs needs to be classed as next day. Then i have to
add 4
days to that new date
any help appriciated
thanks in advance
brian
--