"Frank Kabel" wrote:
Hi
=WORKDAY(A1,A2)
--
Regards
Frank Kabel
Frankfurt, Germany
"Chris maximus" <Chris schrieb im
Newsbeitrag ...
I guess I should have explained mo Cell a1 has date (12/01/04),
cell a2
has number of work days (42), I need to add the two and get end date,
where
42 will be read as workdays, and would return a date of 2/03/05
instead of
1/12/05.
"Frank Kabel" wrote:
Hi
use WORKDAY for this
Note: You have to install the Analysis toolpak Addin for this
function
--
Regards
Frank Kabel
Frankfurt, Germany
"Chris Maximus" <Chris schrieb
im
Newsbeitrag
...
I want to have a spreadsheet where I add a workday number to a
date
and get
the end date, like MS Project. What formula would I use to get
the
result to
show the duration as wrok days?