View Single Post
  #2   Report Post  
Frank Kabel
 
Posts: n/a
Default

Hi
use WORKDAY for this

Note: You have to install the Analysis toolpak Addin for this function

--
Regards
Frank Kabel
Frankfurt, Germany

"Chris Maximus" <Chris schrieb im
Newsbeitrag ...
I want to have a spreadsheet where I add a workday number to a date

and get
the end date, like MS Project. What formula would I use to get the

result to
show the duration as wrok days?