6 months of working days
=NETWORKDAYS("12/10/05","20/10/05")
usually works for me that would give the result 7
You can replace the "12/10/05" with cell references/formulas to get the same
result
e.g. =NETWORKDAYS(R14,R15)
where R14 = 12/10/05
and r15 = 20/10/05
"Jennifer" wrote:
Hi,
I'm trying to figure out how to calculate what 6 months of working days
would be. I've tried the various Networkdays formating, perhaps I'm using
the wrong format for this. Can anyone help?
--
Thanks!
-Jennifer
|