If the date is in A1, rather than a simple =A1+5
try =A1+5+(WEEKDAY(A1+5)=7)*2+(WEEKDAY(A1+5)=1)
--
Gary's Student
"JE McGimpsey" wrote:
Take a look at WORKDAYS() in XL Help. This is an Analysis Toolpak Add-in
function (Tools/Add-ins...)
In article ,
lkoyne wrote:
How do I calculate Dates (ie 10/11/05+5) to get only Week Days, not weekend
days??
|